| January 2008: |
The Progress so far at the apollo 3 site.
|
| October 1st 2007: |
Main structure of Steelwork, Cladding & Roof complete. Glazing 90% complete. Steelwork & Cladding for lift tower + steelwork for 1st floor walkways progressing. Internal partitioning underway
|
| August 1st 2007: |
Steelwork & Cladding virtually complete. First floor installed. Concrete floor screeds being laid. First coats of tarmac to roadways & car parking areas
|
| June 28th 2007: |
Steelwork in kit form for the left-hand block, to be erected within the next two weeks. Foundations now complete.
|
| June 28th 2007: |
Steelwork for the right-hand block is erected
|
| June 1st 2007: |
Groundworks, foundations & drainage works continue on site
|
| May 2007: |
Buckingham's Apollo 3 Already A Success
The Buckingham based third Apollo office development can already be heralded a success. After only beginning construction on the site on the 23 April 2007 only 14 of the 20 office suites remain available to purchase.
Click Here to view complete press release |
| May 2007: |
Site clearance & drainage works begin
|
| 23rd April, 2007: |
Building work starts with contractor’s clearing site & digging out foundations and drainage. Estimated time to completion: 32 weeks. Completion: December 2007.
|