Apollo3: HOME Apollo 3: LINKS Apollo3 - FUNDING Apollo 3 - CONTACT
Apollo3: Freehold Offices to buy or rent in Buckinghamshire, Northamptonshire, Oxfordshire, Milton Keynes, Aylesbury, Bicester and Silverstone. Apollo 3 - Freehold Offices to buy or rent in Buckinghamshire, Northamptonshire, Oxfordshire, Milton Keynes, Aylesbury, Bicester and Silverstone.
Apollo3 - MASTER PLAN Apollo3 -OFFICE SPECIFICATIONS Apollo3 - LOCATION Apollo 3 - BUYERS PACK OTHER APOLLO PROJECTS Apollo3: LOCAL ECONOMY Apollo 3 : Press Comments Press Releases Apollo 3 Gallery
 
Latest News
January 2008:

The Progress so far at the apollo 3 site.

The progress so far The progress so far
The progress so far  

 

October 1st 2007:

Main structure of Steelwork, Cladding & Roof complete. Glazing 90% complete. Steelwork & Cladding for lift tower + steelwork for 1st floor walkways progressing. Internal partitioning underway

Steelwork, Cladding & Roof complete Steelwork, Cladding & Roof complete
Steelwork, Cladding & Roof complete
August 1st 2007:

Steelwork & Cladding virtually complete. First floor installed. Concrete floor screeds being laid. First coats of tarmac to roadways & car parking areas

Groundworks, foundations & drainage works continue on site Groundworks, foundations & drainage works continue on site
Groundworks, foundations & drainage works continue on site Groundworks, foundations & drainage works continue on site
Groundworks, foundations & drainage works continue on site  
June 28th 2007:

Steelwork in kit form for the left-hand block, to be erected within the next two weeks. Foundations now complete.

Steelwork in kit form for the left-hand block, to be erected within the next two weeks. Foundations now complete.
June 28th 2007:

Steelwork for the right-hand block is erected

Steelwork for the right-hand block is erected
June 1st 2007:

Groundworks, foundations & drainage works continue on site

Groundworks, foundations & drainage works continue on site Groundworks, foundations & drainage works continue on site
Groundworks, foundations & drainage works continue on site Groundworks, foundations & drainage works continue on site
May 2007: Buckingham's Apollo 3 Already A Success
The Buckingham based third Apollo office development can already be heralded a success. After only beginning construction on the site on the 23 April 2007 only 14 of the 20 office suites remain available to purchase.
Click Here to view complete press release
May 2007:

Site clearance & drainage works begin

Site clearance & drainage works begin Site clearance & drainage works begin
23rd April, 2007:

Building work starts with contractor’s clearing site & digging out foundations and drainage. Estimated time to completion: 32 weeks. Completion: December 2007.